Nov 1, 2007 - More wiring for electronics done. Dave and I went to look for flooring..
Nov 2-7, 2007 - More wiring for electronics done. Talked with guy about doing chimney. Waiting on plumber so we can get an inspection done. Suppose to have staining of the outside started this week.
Nov 9 - 10, 2007 - Cleaning of wood being done, they're preparing for staining.
CLICK ---->HERE<---- TO SEE LARGER PICTURES
Nov 12-13, 2007 - The staining was done.. WOW it looks a LOT better check out the pictures! There is some places darker then others.. lets wait to see what it looks like in a couple of days.
Nov 14, 2007 - Inspection done.. Just a few minor things this need fixing. We can start with inside now!
Nov 16, 2007 - Some interior walls and a railing put on stairs.
Nov 16, 2007 - Some interior walls near stairs finished and some walls in my office and hall way to Dave's office done..I hear insulation goes in on the 23-24 of Nov. then they start with drywall I think the following week.
Nov 17-24, 2007 - Some more of the interior walls done and some framing around the windows.. Banister for stairs installed. Mantel above fireplace put on.