Sep 1, 2007 - Suppose to meet with a tile guy. Some windows are in the wrong place.. some of the glass was tempered and weren't installed in the right place.

picture picture

Sep 3, 2007 - Jacuzzi bathtub, SEE HERE was delivered today.. was too big for truck Dave went to pick it up in. Front porch was started and worked on. Windows put in correct place. Met with a guy who does cabinets.

picture picturepicture picturepicture

Sep 4, 2007 - More of the porch done. Framing for shower on 1st and 2nd floor done. Tub put in and framed for master bath. We are getting to the stage where we need to pick out ceiling fans, lighting, tile ect... My office and a lot of the basement walls will be done in tounge and groove knotty pine.
picture


picture picturepicture picture

Sep 5, 2007 - Doors installed, Footers for garage apartment porch poured and and for fireplace.. Got a guy to do ALL the cabinets in the house.. They will be made of knotty pine.

Sep 6, 2007 - Sorry all but my MINI (those who know me know what I'm talkin' about) was begging for attention soooooo........ I didn't get any pics today but went by the place earlier today and they were adding a back deck to house... Roof tiles will be delivered tomorrow I hear, and the roofer will be here on Saturday.. Dave and I went and picked out some nice ceramic tiles for the breezeway, master bath, main bath, and the basement bathroom floor...You'll see by pics later on...

picture picturepicture picture

Sep 7-8, 2007 - Back deck to house and deck on garage finished. Dave and I went to look at some lighting and ceiling fans.. Roofers were suppose to be here today (8th).. Shingles were delivered yesterday (7th).. Met with landscaper yesterday..
The exterior walls of the basement will look like the below pic.
picture


Sep 9-10, 2007 - Nothing done!

Sep 11, 2007 - Roofers didn't come yet. Dave met with concrete guys to do the back deck, with plumber, and with cabinet maker.

picture
Sep 12, 2007 - Roofers started. Says they should be done on Friday.

Sep 13, 2007 - Roofers did some more. Plumbers put in more pipe.. went and looked at some stones for the fire place.

Sep 14, 2007 - No roofers today its raining. but the contractors are here doing some caulking and working on the front porch.

picturepicture picturepicturepicture

Sep 15, 2007 - Sorry no pictures yesterday.. It was raining most of the day. Railings on front porch put on. Some were warped so we have to get more from Southland.. Siding added to house...Roof probably will be finished today.. They were still working on it when I got pictures.

Sep 17, 2007 - Nothing was done to house today. Builders won't be back till Friday they only work on it Fridays and Saturdays now.

picture

Sep 18, 2007 - Pipes put in for sewer. Electrician put in meter box.

picture

Sep 19, 2007 - Solar panels put on. Plumbers put tub in basement?

picturepicturepicturepicture

Sep 20, 2007 - Dave and I went to check out the cabinets being made... looking great! Example of the door and 2 of the actual cabinets for kitchen..Got cat door, a necessity with 5 cats. AC and insulation guys working today.

picturepicturepicture

Sep 21, 2007 - Some more doors installed. Some boxing done to garage.

picturepicturepicture

Sep 22, 2007 - Some siding done on the house.

Sep 25 - 27 2007 - Not much happened. The electricians wired from box to house and plumbers layed pipe from well to house.

picturepicturepicturepicture

Sep 28 2007 - Some siding done on the garage. One side done. Some plumbing done earlier in the week or last week. Some A/C vent openings put in.